Tuesday, July 8, 2008

Starting of Earth-digging for the foundation work of Hostel Contraction.










Dear Readers,

Best wishes from the staffs and students of Ngari Education Society.

We finished with the temporary House Construction for the supervisors and store rooms for construction materials, two block of Housing earth level also complicated and contractor marking for foundation and pillar side.

As the begin of monsoon, transporting materials are very hard. Unfortunately, the bored well that drilled last time, does not have sufficient water for construction which is the major problems that is being faced at the moment. The previous bore-well we drilled for 230 fts underground.

So, this time we are expecting to drill one more Borewell with the hopes for more water. Drilling of new bore well will cost Rs. 36,000.00 and donors are most welcome and appreciated.

Due to the shortage of funds for the Hostel construction, students have to work collectively digging the earth during weekend holidays. We hope you will also join us with the financial supports in order to complete the long awaited project.

For further clarification contract with our Mail ID serajeygngarimonks@yahoo.co.in or skype ID: Sera Jey Ngari.

With best wishes and our prayers are with all of you all the time. Catch with you again in our next dairy.